Apartment Don Mueang Si Kan, Bang Khen, Bangkok |
1 Apr 19 – 30 Jun 20 (Underconstruction) |
- Structural Work - Architectural Work - Electrical Work - Sanitary Work |
35,152,531.93 |
Mrs. Pacharee Rungsomboon |
Renovation of Deevana Plaza Krabi Aonang Aonang Soi 8, Aonang Beach, Aonang, Muang, Krabi |
22 Jun 18 – 30 Nov 18 |
- Architectural Work - M&E Work |
17,595,415.39 |
Deevana Hotel and Resort Co., Ltd. |
T2, T3 Wind Farm Substation Thepharak District, Nakhon Ratchasima Province |
10 May 18 – 30 Jun 18 |
- Equipment Foundation - Control Building - External Wor |
12,938,809.00 |
D.B.T. Engineering Co., Ltd. |
4-Storeyed House Soi Ratchadaphisek 42 Yaek 9, Ratchadaphisek Road, Chan Kasem, Chatuchak, Bangkok |
22 Jun 18 – 22 Oct 19 (Underconstruction) |
- Structural Work - Architectural Work - M&E Work - Landscape Work |
17,000,000.00 |
Mr. Dechapol Lamwilai |
Wind Farm Substation : Hanuman Project Chaiyaphum Province HNM 1-8 : Ban Sap Sai O, Tha Kup, Sap Yai, HNM 5-9 : Ban Yang Kiao Faek, Wa Ta Baek, Thep Sathit HNM 10 : Kok Pad Pattana, Bamnetnarong |
20 Jun 17 – 30 Jun 18 |
- Equipment Foundation - Control Building - M&E Work |
46,000,000.00 |
ABB Limited |
5-Storeyed Apartment Soi Soonvijai Soi Petchburi 47, New Petchburi Road, Huaykwang, Bangkok |
1 Dec 16 – 31 Jan 18 |
- Structural Work - Architectural Work - M&E Work - Landscape Work |
29,500,000.00 |
Mr. Prasong Rungsomboon |
Riva Cafe |
13 Oct 16 - 28 Feb 17 |
- Architectural Work - M&E Work - Interior Work |
6,282,607.11 |
Riva Arun Co., Ltd. |
Deevana Krabi Resort Klonghaeng Road, Ao Nang, Muang Krabi, Krabi |
20 Jun 16 - 19 Mar 17 |
- Structural Work - Architectural Work - M & E Work |
63,000,000.00 |
Deevana Hotel and Resort Co., Ltd. |
Structural Work The Heritage Kempinski Hotel Yangon Strand Road, Kyauktada Township, Yangon, Myanmar |
1 Apr 16 – 4 Aug 17 |
- Demolition Work - Structural Work - Material Salvage from Demolition |
68,950,000.00 |
Kanok Furniture & Decoration Co., Ltd. |
Architectural Work (Public Area) Floor 37, 38 and 39 Rosewood Hotel Phnom Penh Preah Ang Non (St.102), Phnom Penh, Cambodia |
1 Feb 16 – 15 Aug 16 |
- Architectural Work |
2,698.000.00 |
Koncise Co., Ltd. |
The Villa Ao Nang Resort Ao Nang, Muang Krabi, Krabi |
15 Nov 14 – 30 Jul 16 |
- Structural Work - Architectural Work - Hardscape Work - Site Drainage Work |
98,935,620.63 |
The Villa Ao Nang Co., Ltd. |
PROJECT |
PERIOD
OF WORK |
TYPE
OF WORK |
CONTRACT
PRICE (BAHT) |
CLIENT |
Proud Phuket Hotel Sakhoo, Thalang, Phuket |
15 Aug 14 – 31 Mar 16 |
- Structural Work - Architectural Work - External Work |
129,500,000.00 |
Suwatnapa Co., Ltd. |
The Primary and Secondary Building HeadStart International School Muang Phuket, Phuket |
1 Jun 14 – 28 Feb 15 |
- Structural Work |
30,600,000.00 |
HeadStart Education Center Co., Ltd. |
Chaiyosburanas’ Clubhouse Romruen Village, Talingchan, Bangkok |
1 Mar 14 – 1 Aug14 |
- Structural Work - Architectural Work - Interior Work - M & E Work |
13,400,000.00 |
Khun Sarinthip Chaiyosburana |
Bank Protection Work Avadina Hills Thalang, Phuket |
15 Jan 14 – 1 Aug14 |
- Structural Work |
25,000,000.00 |
Bang Tao Beach Limited |
Infrastructure Work Phase II Layan Hill Residence Thalang, Phuket |
9 Aug 13 – 30 Dec 14 |
- Structural Work - Architectural Work |
28,500,000.00 |
Stang Co., Ltd. |
Showroom of Honda Hua Talay Hua Talay, Muang, Nakhonratchasima |
18 Jul 13 – 30 Jun 14 |
- Structural Work - Architectural Work - M & E Work |
28,000,000.00 |
Nakhonratchasima Honda Automobile Co., Ltd. |
Renovation of Centara Hotel and Convention Centre Prachasamosorn Road, Khon Kaen |
15 Jul 13 – 25 Jan 14 |
- Renovation Work |
25,000,000.00 |
Khon Kaen Buri Co., Ltd. |
MFL, ENG, Front Hard Court, Sport Pavilion Bangkok Patana School Lasalle Road (Sukhumvit 105), Bangna, Bangkok |
3 Jun 13 – 20 Aug 13 |
- Structural Work - Architectural Work |
32,652,023.20 |
Bangkok Patana School Foundation |
Refurbishment and Finishing Work of Mock-Up Room A, C & D in Clubhouse Miracle Hua Hin Resort Cha-am, Petchburi |
16 Jul 12 – 10 Aug 12 |
- Refurbishment and Finishing Work - M&E Work |
1,129,532.71 |
BCEG Thai International Co., Ltd. |
Landscape Work The Master Golf Arena 28 Soi Yothinpatta 3, Praditmanuthum Road, Kongchan, Bangkapi, Bangkok |
2 May 12 - 30 Apr 14 |
- Landscape Work |
48,143,733.12 |
The Master Golf Area Co., Ltd. |
Landscape Work Fisherman's Resort - Phase 2 Haad Samran Beach, Petchburi |
2 May 12 - 18 Jun 12 |
- Landscape Work |
2,297,119.25 |
Haad Samran Co., Ltd. |
Interior Work, Building A The Master Driving Range, Building A 28 Soi Yothinpatta 3, Praditmanuthum Road, Kongchan, Bangkapi, Bangkok |
1 Apr 12 - 31 July 12 |
- Interior Work |
63,500,000.00 |
The Master Golf Area Co., Ltd. |
Water Treatment Tank BMG Summer Place Villas Hin-Lek-Fai Sub District, Hua-Hin District, Prachuabkirikha |
1 Jun 11 – 4 Jan 12 |
- Structure Work - Architecture Work |
6,396,000.00 |
Thai Nordic Property Co., Ltd. |
PROJECT |
PERIOD
OF WORK |
TYPE
OF WORK |
CONTRACT
PRICE (BAHT) |
CLIENT |
Phothalai Fairway, Building A Phothalai The Thai Wellness Center 28 Soi Yothinpatta 3, Praditmanuthum Road, Kongchan, Bangkapi, Bangkok |
21 Mar 11 – 31 Jul 12 |
- Structure Work - Architecture Work |
86,500,000.00 |
Saeng Udom Karn Kae Ha Co., Ltd. The Master Golf Arena Co., Ltd. |
Wakeboard Area and Waterpark Area Black Mountain Water Park Hin-Lek-Fai Sub District, Hua-Hin District, Prachuabkirikhan |
16 Mar 11 – 31 Mar 12 |
- Structural Work - Architectural Work - Landscape Work - Electrical System - Sanitary System - Waterpark Equipments |
214,000,000.00 |
Black Mountain Water Park Co., Ltd. |
3-Storey Hotel and 2-Storey Seminar Building Haad Sarmran Hotel Chao Samran Beach, Phetchburi |
14 Feb 11 – 18 Jun 12 |
- Structural Work - Architectural Work - Air Conditioning System - Electrical System - Sanitary System |
32,000,000.00 |
Haad Samran Co., Ltd. |
Renovation of Bedrooms for 2 and 3 Beds |
1 Dec 10 – 28 Feb 11 |
- Architectural Work |
3,212,078.80 |
Huahin Vitthayalai School |
Wall Repaint and Installing New Carpets |
15 Nov 10 – 22 Dec 10 |
- Architectural Work |
1,532,605.00 |
Powerwave Technology |
Renovation of Fisherman’s Village Resort |
1 Nov 10 – 30 Nov 10 |
- Structure Work - Architecture Work - Landscape Work |
2,067,767.87 |
Haad Saamran Co., Ltd. |
Hardscape Work at Top of Ne Dump |
8 Sep 10 – 7 Sep 11 |
- Hardscape Work |
21,578,670.00 |
Chanitnan Co., Ltd. |
Renovation of Rafa Office |
26 Aug 10 – 6 Nov 10
|
- Interior Work |
2,778,720.79
|
Rafa Design Office Co., Ltd. Rafa Plus Architect Ltd. Rafa Plus Management Co., Ltd. |
A Century Year’s Sala |
7 Jul 10 – 30 Sep 12 |
- Structure Work - Architecture Work |
14,398,848.00 |
Wat Chonprathanrangsarid |
Renovation Of Powerwave Technologies Powerwave Technologies Co., Ltd. Banglamung, Chonburi |
27 Sep 09 – 3 Nov 09 |
- Architectural Work |
11,663,470.14 |
Powerwave Technologies (Thailand) Co., Ltd. |
BMG Summer Club Condominium |
3 May 08 – 1 Mar 10 |
- Structure Work - Architecture Work |
229,043,591.00 |
Thai Nordic Property Co., Ltd. |
6 Type A, 2 Storey Houses |
For 1st State |
- Structure Work excluding External Stair (ST-3) and Retaining Wall - Architecture Work excluding External Stair |
59,472,000.00
|
Thai Nordic Property Co., Ltd. |
Renovation of Andavana Resort & Spa Ko Silay, Rassada, Muang Phuket |
29 Mar 05 - 8 Apr 05 |
- Renovation of Nine Spa Villas to Villas - Renovation of Anda Building to Apartments - Renovation of Vana Building to Apartments - Renovation of Silay Building to Apartment |
17,205,000.00
|
Silay Health Center Co., Ltd. |